(647) 254-0877Get Estimate
Home/Blog/Underpinning
Underpinning

How Is a House Underpinned? The Concrete Underpinning Process, Step by Step

By Patrick Grygoruk · Owner-Operator · 25+ years GTA constructionUpdated November 20267 min read
Get a free estimate Call (647) 254-0877
The short answer

Underpinning deepens a foundation in small, alternating sections called pins. An engineer designs the sequence and the City issues a permit. The crew then digs and pours one pin at a time, never two neighbours together, so the house stays supported. When all pins have cured, the floor is lowered and a new slab is poured. Expect 4 to 8 weeks of planning and 8 to 16 weeks of work.

Key facts
  • Underpinning is done in alternating sections, usually about a metre wide, and no two neighbouring sections are open at once.
  • Engineering and permit processing takes 4–8 weeks before any digging, and active work takes 8–16 weeks on a typical GTA house.
  • Structural underpinning in the GTA costs $35,000–$140,000, and a typical full-basement job is $55,000–$100,000+.
  • Engineer's drawings run $3,000–$6,000, and permit fees are billed at cost on top of the price.
  • Each pin must cure before its neighbours are dug, which is why the job cannot be rushed.

The short version

Underpinning does not lift the house or pour a new foundation in one go. The existing footing stays where it is, and the crew extends the foundation downward underneath it, a small section at a time. That is what makes it safe: at any moment most of the wall is still sitting on the old footing, and only one short section is being worked on.

The method most Toronto houses use is traditional mass-concrete underpinning, also called the pit method. The steps below follow how a typical project runs, from the first site visit to the final inspection.

Step 1: Site review and engineering

Before anything is dug, a structural engineer inspects the house and tests the soil. They record the depth and width of the existing footing, the condition of the walls and the type of soil, which in much of the GTA is clay. The engineer then stamps drawings that show the new depth, the size of each pin and the exact order in which the pins will be poured. Engineering and drawings typically cost $3,000 to $6,000.

Step 2: Permit and notice

The drawings go to the City with a building permit application. Underpinning always needs a permit, and processing plus engineering usually takes 4 to 8 weeks. If you share a wall with a neighbour, they are notified in writing. Permit fees are billed at cost on top of the quoted price, either as a separate line or invoiced once the amount is known.

Step 3: Prepare the basement

The crew clears the space, protects utilities, and sets up access for removing soil. In most Toronto houses that means a small opening, a chute or a conveyor to a bin outside, since there is no room for machines. Temporary shoring goes in where the drawings call for it, for example around a chimney base or a load-bearing wall.

Step 4: Dig and pour the pins, one at a time

This is the core of the job. The drawings divide the walls into numbered sections. The crew digs the first section by hand beneath the old footing to the new depth, sets rebar, forms it and pours concrete. The gap between the top of the new pin and the underside of the old footing is packed with a stiff dry mix so the wall bears fully on the new concrete.

  1. 1Dig pin 1, form and pour. Leave it to cure.
  2. 2Move to pin 4, a few sections away, and repeat.
  3. 3Continue around the walls following the engineer's sequence.
  4. 4Return to the first pass of pins and dig the sections between them once the neighbouring concrete has cured.

Two pins that sit side by side are never open at the same time. That one rule is what keeps the wall supported while the foundation goes deeper.

Ask a contractor

Have a question about your basement?

Ask it here and get a straight answer from a contractor who lowers and waterproofs basements across the GTA. No site visit needed. We reply within 24 hours.

We reply to you directly and never share your details.

Step 5: Lower the floor and add drainage

After every pin has cured and passed inspection, the crew excavates the rest of the floor to the new level. This is the best time to add waterproofing, weeping tile and a sump if the engineer or contractor recommends it, because the walls are open and the work shares the same excavation. A full waterproofing scope on an underpinning job typically adds $6,000 to $15,000.

Step 6: New slab and inspections

Gravel, a vapour barrier and in many cases insulation go down, then a new concrete slab is poured, typically $3,000 to $7,000. The City inspects at set stages and the engineer reviews the work, so the sign-off is documented for future buyers and insurers.

How long it takes and what it costs

StageTypical timeTypical cost
Engineering and drawings2–4 weeks$3,000 – $6,000
Permit processing2–4 weeksBilled at cost
Pin-by-pin underpinning8–16 weeks for the active phase$35,000 – $140,000 for the structural phase
Waterproofing (recommended)Within the active phase$6,000 – $15,000
New floor slabA few days$3,000 – $7,000

A typical full-basement job in a detached house runs about $55,000 to $100,000+. All prices are before HST, which is 13% on the whole pre-tax amount.

What homeowners should expect during the work

  • Noise and dust from breaking out the floor and moving soil, usually on weekdays from morning.
  • Soil bins at the curb, often for weeks, so check street parking and bin rules.
  • Hairline cracks in plaster or drywall upstairs are common, so photograph the house beforehand.
  • Inspections that pause the work. The pour waits until the inspector has signed off.
  • Winter is a normal time for the interior work, since the digging is inside the basement. Exterior waterproofing slows when the ground is frozen.

FAQs about how underpinning works

Planning to lower your basement?

We start with a site visit, measure the footing and walk you through the engineering, permit and schedule, so you know what happens each week. Written, itemized scope, $0 down. Call (647) 254-0877.

Reviewed by Patrick Grygoruk

Owner-Operator at Buildoreno with 25+ years of hands-on GTA construction experience. Last reviewed November 2026.

Home/Blog/How Is a House Underpinned? The Concrete Underpinning Process, Step by Step
Honest answers

Frequently asked questions

No. The house stays on its existing footing while the new concrete is built beneath it in small sections.

Many owners do, since the work is in the basement, but expect noise, dust and restricted access. Larger or deeper jobs are often easier to live through if you move out.

Removing the soil under a whole wall would leave it unsupported. Alternating small pins keep most of the wall resting on the old footing at all times.

Underpinning extends the footings deeper and gives full floor area. Bench footing leaves the footing alone and lowers the central floor, which costs less but takes some floor width along the walls.

Yes. Underpinning requires stamped drawings from a structural engineer, and the City will not issue a permit without them.

Current offers
Prefer to talk? Call +1 647-254-0877
From $300/lin ft

Basement underpinning from $300 per linear foot

Engineered, permitted and City-inspected at every stage. Pay as each phase passes inspection.

* Starting rate for a 2 ft lower on a straightforward foundation with clear access. Depth, soil and shared walls are priced from your inspection. Our minimum project is $3,000. Plus HST; permits billed at cost. Engineering billed at cost unless you bring your own engineer.

Book an inspection →
Credited back

$400 basement inspection, credited back when you hire us

We measure the ceiling height and footings and tell you in writing whether you need underpinning, bench footing or neither — and what each would cost. The fee is credited against the work (up to 10% of the quote).

Book an inspection →
Free add-on

Free sump pit and discharge line with any full-perimeter underpin

A lowered basement needs somewhere for water to go. The pit, liner and discharge line are included in every full-perimeter job.

Claim this offer →
Free · No obligation

Want to see how your basement would be lowered?

We measure the footing and walk you through the engineering, permit and schedule, then give you a written scope and price. Free, no obligation, $0 down.

Call (647) 254-0877
Free on-site estimateRegistered & WSIB coveredBBB Accredited Business10-year written warranty

Get your free estimate

Takes 30 seconds. No obligation.

🔒 We'll never share your info. One call, one estimator.